KSERC · Regulation · 7 Feb 2020

KSERC Renewable Energy and Net Metering Regulations, 2020

The Kerala regulator's rulebook for rooftop solar: who can connect, how net metering and banking of surplus units work, and how the surplus is paid for. It has been amended since; KSEB circulars cite it as the 2020 Regulations and their amendments.

Reference: No. 1204/D(T)/2019/KSERC

Key points

  • Net metering covers prosumer systems from 1 kW to 1,000 kW on the AC side of the inverter, limited to the sanctioned connected load or contract demand.
  • Surplus units in a billing period are banked and carried forward through the settlement period.
  • The net balance at the end of the settlement period is paid at the Average Power Purchase Cost approved by KSERC, with interest if payment is delayed beyond 30 days.
  • A prosumer can apply to wheel surplus solar units to another of their own premises.
  • Systems above 1 MW, captive consumers and independent power producers are covered by a separate chapter.

What this means for you

Some details have changed through later amendments, so read this with the newest KSEB circulars. Our guides explain how the rules play out on a home bill today.

Stuck at the section office?

We file the feasibility, registration and net-meter paperwork for every SEDNA installation.

Ask on WhatsApp

Summary by SEDNA Energy Systems. The PDF is the authority; if anything here differs from it, the document wins.

Next Step · Free Roof Assessment

Ready to see what your roof could save?

One hour on your roof, measured with instruments rather than guessed over the phone, and you have the real numbers for your own house.

  • 4.9 on Google
  • 2,500+ installations
  • MNRE-approved
  • Since 2009

Free roof inspection · no obligation

Start with your bill.

1 / 3
  1. Your bill
  2. Your system
  3. Your details
  • Free inspection
  • No obligation
  • Reply within 24 hours
CallWhatsAppGet quote