KSEB · Circular · 14 May 2026

KSEB on-grid solar connectivity procedure (May 2026)

KSEB's instructions to section offices on rooftop solar applications: feasibility within 15 days (ideally 2 working days), registration within 30 days of feasibility, grid connection within 7 days of the agreement, and no rejecting complete applications.

Open the circular (PDF) 0.9 MB · in Malayalam

Reference: No. Solar Projects/PMSG/2026-27

Key points, in English

  • Feasibility: the application (Annexure-A) goes in with a ₹1,000 fee, and the office issues an acknowledgement and cash receipt on the spot.
  • Applications are accepted on working days from 9:00 to 15:00. Offices may not ask for documents beyond the list.
  • On the first working day of every month, the office puts the transformer feasibility report on its notice board.
  • Plant capacity is taken as the inverter capacity or 85% of the panel capacity, whichever is higher.
  • Feasibility is decided within 15 days at most, and offices should try to decide within 2 working days. The certificate can be sent by email, WhatsApp or post, and is valid for 30 days.
  • Registration (Annexure-B) within 30 days of feasibility, at ₹1,000 + GST per kW, with a single-line diagram by an A or B class contractor, inverter, panel and isolator specifications, and type-test certificates for the MCB, ELCB and inverter.
  • Single-phase inverters are allowed only up to 5 kW. Registration is valid for one year, extendable by six months.
  • Installation is by a licensed contractor, who submits Annexure-C. A meter test certificate from an NABL-accredited lab is mandatory.
  • Up to 50 kW, no Electrical Inspector approval is needed; the contractor's completion certificate is enough.
  • After Annexure-C, the Annexure-D agreement is signed on ₹200 stamp paper, and grid connection follows within 2 working days (7 days at most).

What this means for you

The steps for a home system are the familiar ones, but the time limits are now in writing. If a section office asks for papers that are not on the list, or holds a complete application, this is the circular to point to.

Stuck at the section office?

We file the feasibility, registration and net-meter paperwork for every SEDNA installation.

Ask on WhatsApp

Summary by SEDNA Energy Systems. The PDF is the authority; if anything here differs from it, the document wins.

Next Step · Free Roof Assessment

Ready to see what your roof could save?

One hour on your roof, measured with instruments rather than guessed over the phone, and you have the real numbers for your own house.

  • 4.9 on Google
  • 2,500+ installations
  • MNRE-approved
  • Since 2009

Free roof inspection · no obligation

Start with your bill.

1 / 3
  1. Your bill
  2. Your system
  3. Your details
  • Free inspection
  • No obligation
  • Reply within 24 hours
CallWhatsAppGet quote